Owner’s Engineering – Belgium

  Client:  Vasco & Alro Location:  Dilsen Stokkem wind farm, Belgium Project size:  12MW (6 Senvion MM100) Period:  2015-2017 Work – WTG package tender preparation and management – TSA contract negotiation – BOP civil & electrical follow up – Construction management

Component inspection – Belgium

  Client:  Storm Location:  Meer, Belgium Period:  2014 Work – Visual inspection of nacelle, blades and tower section – Lightning protection system check/measurements for blades

Owner’s engineer – Oman

  Client:  Masdar Location:  Dhofar wind farm Project size:  50MW Period:  2016 Work – Resident consultant for 6 weeks in Abu Dhabi – EPC Tender technical documentation analysis – Bidder technical documentation analysis – Gap analysis of bidder’s offers – Overall offer ratings for each bidder (6) – Recommendations to client

Component inspection – Belgium

  Client:  Storm Location:  Minderhout, Belgium Period:  2017 Work – Visual inspection of nacelle, blades and tower section – Lightning protection system check/measurements for blades

Resident Engineer – Turkey

  Client:  Zaf Group/Tefirom Location:  Sembuk wind farm, Turkey Project size:  27MW (9 Vestas V112 3MW) Period:  2014 Work – Daily toolbox talks – Daily walks around and quality audits – Contractor’s documentation review & approval – Weekly reporting to client – Wind turbine inspections – Snag List preparation and follow up – Support for[…]

WTG transformer verification – France

  Client:  Quadran Location:  Dainville, France Project size:  24MW (12 Vestas V110 2MW) Period:  2017 Work – Follow up on on-site WTG transformer mounting into the nacelles – Visual inspection and torque verification – Compliance verification with transformer manufacturer’s requirements

End of warranty inspection – France

  Client:  Innovent Location:  Valhuon, France Project size:  2MW (1 Enercon E70 2MW) Period:  2015 Work – Wind turbine visual inspection – Blade inspection (by cherry picker)

Wind turbine inspection – France

  Client:  AlpiQ Location:  Gravière wind farm, France Project size:  10.5MW (6 Vestas V66) Period:  2016 Work – Wind Turbine and infrastructure visual inspection – Blade inspection – Gearbox inspection (endoscope) – Gearbox oil analysis

De Aar I&II wind farm

  Country:  South Africa Period:  2016 – 2017 Work 3E has been contracted by Mulillo, one of the main wind farm and PV plant developer and operator in South Africa, to act as Independent Engineer with Duty of Care toward Eskom, the grid operator, to monitor the construction of the 240MW projects. The assignment includes[…]

Fontenai wind farm

  Country:  France Period:  2016 Work French developer IEL relied on 3E to review and better negotiate the Turbine Supply Agreement and O&M contract for the 12MW Fontenai wind farm, in Western France. 3E reviewed the initial Heads of Terms ad is leading the contractual negotiation, focusing on risk shifting, warranty, Liquidated Damages and planning,[…]

Dilsen-Stokkem wind farm

  Country:  Belgium Period:  2015 Work Vasco Group, a Belgian industrial group, was granted the permit for the construction of 4 wind turbines, for a total installed capacity of 8MW, in Dilsen Stokkem, near the border with the Netherlands. 3E was contracted to finalize the electrical ad civil engineering, manage the tendering process for the[…]