Country: Belgium
Period: 2016
Work
Vleemo contracted 3E for the technical Due Diligence of the Port of Antwerpt-right bank project, consisting of 18 Enercon E101 turbines for a total installed capacity of 54MW. The scope of work includes an independent long term energy yield assessment, the review of the building permit and grid connection agreement, as well as the review and gap analysis of the Turbine Supply Agreement and O&M contract from Enercon. 3E acted as Lender’s Techncial Advisor for Belfius, which provides the debt for the project.